Power Interruptions

Be informed with the latest power interruptions of NGCP and BOHECO I

Sat, Oct. 12, 2024

WHAT: BOHECO I Scheduled Power Interruption
WHEN: Saturday, October 12, 2024 from 5:00AM-12:00NN
WHERE: Mun. of Dauis and Panglao
WHY: Bus works and Tapping of new additional 15MVA Transformer and its accessories in Lourdes Substation
We sincerely apologize for the inconvenience this will bring you. We request your patience and understanding on this matter. Rest assured that our team will exert best effort to restore the power the soonest possible time.
For further queries, please call our hotline numbers at 09177147493 or 09199950240

Sat, Oct. 12, 2024

WHAT: NGCP Re-scheduled Power Interruption
WHEN: Saturday, October 5 moved to October 12, 2024 from 4:00AM-6:00AM and one hour in the afternoon
WHERE: Mun. of Carmen, Batuan, Bilar, Oac-Canlambong Dimiao, Sagbayan, Dagnawan-San Jose Inabanga, Maitum-Kang-iras Catigbian
WHY: facilitate on-going Substation project in which there will be a reconfiguration of the existing 138KV switchyard inside NGCP Ubay substation
We sincerely apologize for the inconvenience this will bring you. We request your patience and understanding on this matter as THIS IS BEYOND OUR CONTROL. Rest assured that power will be back to normal once the maintenance activity of NGCP is done.
For further queries, please call our hotline numbers at 09177147493 or 09199950240

Fri, Oct. 11, 2024

WHAT: BOHECO I Scheduled Power Interruption
WHEN: Friday, October 11, 2024 from 8:00AM-4:00PM
WHERE: Landican to Payahan, Buenaventura of Baclayon
WHY: line upgrading
We sincerely apologize for the inconvenience this will bring you. We request your patience and understanding on this matter. Rest assured that our team will exert best effort to restore the power the soonest possible time.
For further queries, please call our hotline numbers at 09177147493 or 09199950240

Tue, Oct. 8, 2024

WHAT: BOHECO I Scheduled Power Interruption
WHEN: Tuesday, October 8, 2024 from 5:01AM-6:00AM
WHERE: Mun. of Baclayon, Albur, Loay, Loboc, Sevilla, Lila, Dimiao, Dauis, Panglao
WHY: tapping and energization of 5MVA Baclayon Substation
We sincerely apologize for the inconvenience this will bring you. We request your patience and understanding on this matter. Rest assured that our team will exert best effort to restore the power the soonest possible time.
For further queries, please call our hotline numbers at 09177147493 or 09199950240

Sat, Oct. 5, 2024

WHAT: BOHECO I Scheduled Power Interruption
WHEN: Saturday, October 5, 2024
WHERE: (6:01AM-4:00PM) Lucob, Bentig, Bonbon, San Isidro, Pangangan Is., Sta. Cruz, Catmonan, Calape
(6:00AM-6:30AM and 3:30PM-4:00PM) Guiwanon, Pinayagan Norte/Sur, Ilijan Norte/Sur, Panaytayon, Cahayag, Banlasan Dacu, Pandan, Matabao, Villanueva, Tubigon; Banlasan Gamay, Abucayan Norte/Sur, Lucob, Ulbojan, Labuon, Binogawan, Cabudburan, Desamparados, Calape
WHY: erection of 69KV poles in preparation for 10MVA Calape Substation
We sincerely apologize for the inconvenience this will bring you. We request your patience and understanding on this matter. Rest assured that our team will exert best effort to restore the power the soonest possible time.
For further queries, please call our hotline numbers at 09177147493 or 09199950240

Fri, Oct. 4, 2024

WHAT: BOHECO I Scheduled Power Interruption
WHEN: Friday, October 4, 2024 from 9:00AM to 4:00PM
WHERE: Brgy. Candasig, Cabad of Balilihan; portion of Rosario, Cortes
WHY: relocation of poles affected by Bridge Construction Project along Candasig, Balilihan and other maintenance activities
We sincerely apologize for the inconvenience this will bring you. We request your patience and understanding on this matter. Rest assured that our team will exert best effort to restore the power the soonest possible time.
For further queries, please call our hotline numbers at 09177147493 or 09199950240