Power Interruptions

Be informed with the latest power interruptions of NGCP and BOHECO I

Fri, Mar. 8, 2024

WHAT: BOHECO I Scheduled Power Interruption
WHEN: Friday, March 8, 2024 from 12:30PM-2:30PM
WHERE: Sitio Daurong, Danao, Panglao
WHY: fixing the 3-phase primary line of Mr. Mario Guerra Beach Resort
We sincerely apologize for the inconvenience this will bring you. We request your patience and understanding on this matter. Rest assured that our team will exert best effort to restore the power the soonest possible time.
For further queries, please call our hotline numbers at 09177147493 or 09199950240

Wed, Mar. 6, 2024

WHAT: BOHECO I Scheduled Power Interruption
WHEN: Wednesday, March 6, 2024 from 10:00AM-3:00PM
WHERE: Brgy. Lomanoy, Lila
WHY: pole relocation and line maintenance
We sincerely apologize for the inconvenience this will bring you. We request your patience and understanding on this matter. Rest assured that our team will exert best effort to restore the power the soonest possible time.
For further queries, please call our hotline numbers at 09177147493 or 09199950240

Tue, Mar. 5, 2024

WHAT: BOHECO I Scheduled Power Interruption
WHEN: Tuesday, March 5, 2024 from 9:30AM-3:30PM
WHERE: Brgy. Cancatac, Corella
WHY: pole relocation and line maintenance
We sincerely apologize for the inconvenience this will bring you. We request your patience and understanding on this matter. Rest assured that our team will exert best effort to restore the power the soonest possible time.
For further queries, please call our hotline numbers at 09177147493 or 09199950240

Sun, Mar. 3, 2024

WHAT: NGCP Scheduled Power Interruption
WHEN: Sunday, March 3, 2024 from 6:01AM-7:00AM and 5:01PM-6:00PM
WHERE: Mun. of Baclayon, Albur, Loay, Loboc, Sevilla, Lila, Dimiao, Dauis, Panglao
WHY: erection of new double circuit steel pole for Corella-Tagbilaran 69KV Line at Corella Substation as part of NGCP Cebu-Bohol Interconnection Project
We sincerely apologize for the inconvenience this will bring you. We request your patience and understanding on this matter as THIS IS BEYOND OUR CONTROL. Rest assured that power will be back to normal once the maintenance activity of NGCP is done.
For further queries, please call our hotline numbers at 09177147493 or 09199950240

Thu, Feb. 29, 2024

WHAT: BOHECO I Scheduled Power Interruption
WHEN: Thursday, February 29, 2024 from 1:00PM-5:00PM
WHERE: parts of Panglao (Bolod, Tawala, Libaong and Daurong Danao), parts of Dauis (Dao, San Isidro, Biking, Catarman, Mayacabac)
WHY: Annual Preventive Maintenance of Bolod Substation Transformer and Equipment
We sincerely apologize for the inconvenience this will bring you. We request your patience and understanding on this matter. Rest assured that our team will exert best effort to restore the power the soonest possible time.
For further queries, please call our hotline numbers at 09177147493 or 09199950240

Thu, Feb. 29, 2024

WHAT: BOHECO I Scheduled Power Interruption
WHEN: Thursday, February 29, 2024 from 7:00AM-11:00AM
WHERE: parts of Panglao (Lourdes, Danao, Poblacion, Doljo, Looc, Bil-isan) Note: Feeder 18 serving parts of Dauis (Tinago, Bingag, Songculan, Tabalong, Mariveles, Totolan, Poblacion) and Tangnan Panglao will start from 6:00AM to 12:00NN due to line upgrading from Tinago-Bingag Double Circuit line
WHY: Annual Preventive Maintenance of Lourdes Substation Transformer and Equipment
We sincerely apologize for the inconvenience this will bring you. We request your patience and understanding on this matter. Rest assured that our team will exert best effort to restore the power the soonest possible time.
For further queries, please call our hotline numbers at 09177147493 or 09199950240