June 17 & 20, 2020

Please be informed that there will be a scheduled power interruption on June 17 and 20, 2020 from 8:00A.M. to 5:00P.M., this is to facilitate pole replacement and line upgrading.

AFFECTED LINE SECTION: Pole # 159/35/22A-1, Single phase line portion of Danao, Panglao

Sat, June 20, 2020

Please be informed that there will be a scheduled power interruption on Saturday, June 20, 2020, this is to facilitate reconductoring of primary lines.

Affected Areas: (6:00AM-6:00PM) From Pole I.D 116/55 – Disconnect Switch, Tawala to Pole I.D 159-35/11, line going to Daurong Danao, Panglao. (6:00AM to 7:00AM & 5:00PM to 6:00PM) Feeder28 – 15MVA, Bolod Substation

Sat, June 20, 2020

Please be informed that there will be a power interruption of NGCP (National Grid Corporation of the Philippines) on Saturday, June 20, 2020 from 6:00AM – 7:00AM & 5:00PM – 6:00PM affecting Loay and Panglao Substations. This is to facilitate the repair of structures along Tagbilaran – Garcia 69KV line.

Affected Areas: Mun. of Baclayon, Albur, Loay, Loboc, Sevilla, Lila, Dimiao, Dauis, Panglao.

Fri, June 19, 2020

Please be informed that there will be a power interruption on Friday, June 19, 2020 from 9:00 A.M. to 4:00 P.M., this is to facilitate construction of 13.2KV double circuit lines and pole replacement.

Affected Areas: From Pole ID # 116-8 to 116-24, Portion of Brgy. Bolod Panglao (9:00AM to 11:00AM); From Pole ID # 116-24 to 116-41, Portion of Bolod-Tawala of Panglao (9:00AM-4:00PM)

Fri, June 12, 2020

Please be informed that there will be a power interruption on June 12, 2020, Friday, this is to facilitate reconductoring of primary lines.

Affected Areas: (6:00AM – 6:30AM & 3:30PM – 4:00PM) 15MVA Bolod Substation; (6:00AM – 4:00PM) From: Pole I.D 116/44 – Disconnect Switch, Tawala to Pole I.D 159-35/15, portion of Danao, Panglao

June 9 & 11, 2020

Please be informed that there will be a power interruption on June 9 and 11, 2020 from 9:30 A.M. to 4:00 P.M.. This is to facilitate line upgrading