Wed, July 15, 2020
Please be informed that there will be a power interruption on Wednesday, July 15, 2020 from 1:00 P.M. to 3:30 P.M., this is to facilitate erection of pole at Malayo Norte and line construction proposed DENR Office connection point at Salvador of Cortes.
Affected Areas: (1:00 PM – 1:15 PM) Feeder 16- From Lincod, Maribojoc to Municipality of Cortes and Antequera; (1:00 PM – 3:30 PM) From Pole # 518/7, Poblacion after Central School to Lapaz of Cortes; (1:00 PM – 2:00 PM) From Pole#1, Poblacion to Malayo Norte, Rosario, Fatima of Cortes
Tue, July 14, 2020
Please be informed that there will be a power interruption on Tuesday, July 14, 2020 from 9:00 A.M. to 4:00 P.M. to facilitate pole replacement of rotten poles & line upgrading at Causwagan Norte, Catigbian.
Affected Areas: Brgy. Causwagan Norte & Mantacida, Catigbian.
July 9 & 13, 2020
Please be informed that there will be a power service interruption on Thursday, July 9 & Monday, July 13, 2020 from 8:00AM to 4:00PM to facilitate pole replacement of rotten poles and reconductoring at Brgy. Candasig – Cabad – Rosario, Cortes.
Affected Areas: Brgy. Candasig, Cabad, Balilihan & Rosario, Cortes
July 4 & 11, 2020
Please be informed that there will be a power interruption on July 4 and 11, 2020, Saturday. This is to facilitate reconductoring, construction of double circuit primary line and erection of additional structure for Panglao Alona Suites, Tawala, Panglao.
Affected Areas: From Pole ID 116/44 – Disconnect Switch, After Traffic light Tawala to Pole ID 116/44 – 35/15, Brgy Road going to Kalipayan, BE Beach Resort of Danao, Panglao (6:00A.M – 4:30P.M); Feeder 28 – 15MVA, Bolod Substation, (6:00AM to 6:30AM & 3:30PM to 4:30PM)
Fri, July 10, 2020
Please be informed that there will be a power interruption on Friday, July 10, 2020 from 9:00AM to 4:00PM to facilitate line relocation at Brgy. Buenavista, Carmen near Elementary School.
Affected Areas: Brgy. Buenavista, El Progreso, Montesuerte and Villafuerte, Carmen
July 3, 7, 10, 2020
Please be informed that there will be a power interruption on July 3, 7 and 10, 2020 from 9:00 A.M. to 4:00 P.M, this is to facilitate construction of 13.2KV double circuit lines and pole replacement.
Affected Line Section: From PoleID # 116-24 to 116-41, Purok 4 and portion of Purok 5, Bolod of Panglao.