Power Interruptions

Be informed with the latest power interruptions of NGCP and BOHECO I

Tue, March 4, 2025

WHAT: BOHECO I Scheduled Power Interruption

WHEN: Tuesday, March 4, 2025

WHERE: Boundary Liboron Pole #180 to Muhon, Tultugan, Calape Pole #195/ Ortigas Fishpond from 6:01AM to 5:00PM

Brgy. Liboron Pole #165 to Boundary Tultugan Pole #180 from 6:01AM to 6:30AM and 4:30PM to 5:00PM

WHY: Facilitate the construction of BOHECO I 69kV Sub-Transmission line from Brgy. Liboron to Tultugan Calape 10MVA Substation.

We sincerely apologize for the inconvenience this will bring you. We request your patience and understanding on this matter. Rest assured that our team will exert best effort to restore the power the soonest possible time.
For further queries, please call our hotline numbers at 09177147493 or 09199950240

Fri, February 28, 2025

WHAT: BOHECO I Scheduled Power Interruption

WHEN: Friday, February 28, 2025

WHERE: Municipalities of Alburquerque, Loay, Loboc, Sevilla, Lila and Dimiao (except Brgys. Oac – Canlambong) from 6:00AM to 11:00AM

Municipality of Baclayon and Tanday, Corella/ BWUI from 1:00PM to 5:00PM

WHY: Facilitate Annual Preventive Maintenance Servicing of its Power Transformer and Equipment oLourdes and Bolod Substation.

We sincerely apologize for the inconvenience this will bring you. We request your patience and understanding on this matter. Rest assured that our team will exert best effort to restore the power the soonest possible time.
For further queries, please call our hotline numbers at 09177147493 or 09199950240

Thu, Feb. 27, 2025

WHAT: BOHECO I Scheduled Power Interruption

WHEN: Thursday, February 27, 2025

WHERE: Brgys. Tinago – Tabalong – Poblacion (Dauis) – Totalan – Catarman, Dauis, Lourdes – Poblacion (Panglao) – Doljo – portion Danao, Panglao. Modala/Bellevue Hotel from 6:00AM to 11:00AM

Brgys. Dao – San Isidro – Biking, Dauis, Bolod – Tawala – Daorong, Danao, Panglao. McDo/ Jollibee/ Blue Water/ BE Grand/ Airport/ Eskaya/ Oceanica Resorts from 1:00PM to 5:00PM

WHY: Facilitate Annual Preventive Maintenance Servicing of Power Transformer and Equipment of Lourdes and Bolod Substation.

We sincerely apologize for the inconvenience this will bring you. We request your patience and understanding on this matter. Rest assured that our team will exert best effort to restore the power the soonest possible time.
For further queries, please call our hotline numbers at 09177147493 or 09199950240

Wed, Feb. 26, 2025

WHAT: BOHECO I Scheduled Power Interruption

WHEN: Wednesday, February 26, 2025

WHERE: Mun. of Tubigon, Clarin, Inabanga, and Calape(except Liboron/Tultugan, Calape, Libertad/Buenos Aires, Tubigon & Dagnawan – Cambitoon – San Jose, Inabanga) from 6:00AM to 11:00AM

Mun. of Loon (except Brgys. Lintuan – Song-on) – Tultugan – Liboron – Cabayugan – Camias, Calape, Cansibuan – Canlaas – Quinapon-an, Antequera – Candavid, Maribojoc. from 1:00PM to 5:00PM

WHY: Facilitate Annual Preventive Maintenance Servicing of Power Transformer and Equipment of Macaas and Catagbacan Substation.

We sincerely apologize for the inconvenience this will bring you. We request your patience and understanding on this matter. Rest assured that our team will exert best effort to restore the power the soonest possible time.
For further queries, please call our hotline numbers at 09177147493 or 09199950240

Tue, February 25, 2025

WHAT: BOHECO I Scheduled Power Interruption

WHEN: Tuesday, February 25, 2025

WHERE: Cortes Hospital, Alturas Piggery, Lourdes, Malayo Norte – Rosario – Fatima, Cortes (6AM to 11AM)

Mun. of Maribojoc, Antequera, Cortes, Corella, Sikatuna – Datag Norte/Sur, Balilihan – Libertad, Baclayon – Cantiguib, Dangay, Sitio Canlimpong, Basasdacu, Albur – Song-on – Cabadug(NGCP Repeater) – Lintuan – Cabug, Loon (1:00PM to 5:00PM)

WHY: Facilitate Annual Preventive Maintenance Servicing of Power Transformer & Equipment of Cortes and Maribojoc Substation.

We sincerely apologize for the inconvenience this will bring you. We request your patience and understanding on this matter. Rest assured that our team will exert best effort to restore the power the soonest possible time.
For further queries, please call our hotline numbers at 09177147493 or 09199950240

Mon, Feb. 24, 2025

WHAT: BOHECO I Scheduled Power Interruption

WHEN: Monday, February 24, 2025

WHERE: Mun. of Carmen, Batuan, Bilar and Brgys. Oac to Canlambong Dimiao, San Jose, Batuan to Mun. of Sagbayan to Dagnawan to San Jose, Inabanga to Kang-iras, Catigbian(6:00AM to 11:AM)

Mun. of Balilihan, Catigbian, San Isidro and Buenos Aires, Libertad, Tubigon(1:00PM to 5:00PM)

Note: Pob.(Sitio School Site), San Isidro, Katipunan, Langtad, San Ramon and Mantalongon, Sagbayan interruption will be extended from 6AM to 5PM due to line correction and line maintenance activities

WHY: Facilitate Annual Preventive Maintenance Servicing of Power Transformer & Equipment of Sagasa and Carmen Substation.

We sincerely apologize for the inconvenience this will bring you. We request your patience and understanding on this matter. Rest assured that our team will exert best effort to restore the power the soonest possible time.
For further queries, please call our hotline numbers at 09177147493 or 09199950240